A Level Accounting (9706)•9706/12/O/N/21
A Level Accounting (9706) — 9706/12/O/N/21, Question 22
business employs 20 workers production staff. Each worker employed for 40 hours per week at a rate of $70 per hour. Bonus is calculated 20% basic rate per hour for each product manufactured above 120 units per employee. In a week, each employee produced 145 units. What were the total wages for the week?

Answer choices
- A$7020
- B$6984
- C$10784
- D$10920
Explanation
Ambiguous bonus calculation prevents exact total wages Steps: - Basic pay per worker: 40 hours × 2,800. - Total basic pay for 20 workers: 20 × 56,000. - Extra units per worker: 145 – 120 = 25. - Bonus rate: 20% × 14 per extra unit (assuming per-unit payment), bonus per worker: 25 × 350, total bonus: 20 × 7,000. - Total wages: 7,000 = 63,000; choices suggest possible error in problem numbers (e.g., rate as 6,300–7/hour without full bonus). - C: May assume higher rate or include unrelated costs (e.g., $70/hour for fewer workers plus overtime). - D: Likely overestimates bonus …
Topic: Standard costing
Practice more A Level Accounting (9706) questions on mMCQ.me