A business absorbs its overheads on the basis of direct labour hours. The following information is provided. Overheads actual 96000 budgeted 48000. Direct labour hours actual 19000 budgeted 12000. By how much are overheads under or over absorbed?

Answer choices
- Aover absorbed by $14000
- Bunder absorbed by $19000
- Cover absorbed by $19000
- Dunder absorbed by $9000
Explanation
Overhead absorption variance calculation Steps:
- Calculate predetermined absorption rate: budgeted overheads ÷ budgeted direct labour hours = 48,000 ÷ 12,000 = $4 per hour.
- Calculate absorbed overheads: absorption rate × actual direct labour hours = 76,000.
- Calculate variance: absorbed overheads − actual overheads = 57,000 = $19,000 over absorbed. Why C is correct:
- Over absorption is defined as the excess of absorbed overheads over actual overheads using the predetermined rate formula, resulting in $19,000 here. Why the others are wrong:
- A. 19,000 from the calculation.
- B. Under absorption assumes actual overheads exceed absorbed, but absorbed exceeds actual.
- D. $9,000 under assumes a smaller opposite variance not supported by the figures. Final answer: C