A Level Accounting (9706)•9706/11/O/N/18
A Level Accounting (9706) — 9706/11/O/N/18, Question 25
A business absorbs overheads based on machine hours. During last month it had the following results. actual machine hours 7590 budgeted machine hours 16820 actual overheads 7310 budgeted overheads 16820 Which statement is correct?

Answer choices
- AOverheads were over-absorbed by $1000.
- BOverheads were under-absorbed by $1000.
- COverheads were under-absorbed by $2000.
- DOverheads were over-absorbed by $2000.
Explanation
Overheads Absorption Variance
Steps:
- Calculate predetermined rate: budgeted overheads ÷ budgeted machine hours = 16820 ÷ 16820 = $1 per machine hour.
- Calculate absorbed overheads: 7590.
- Compare to actual: absorbed 5590 = $2000 (over-absorbed).
Why D is correct:
- In absorption costing, over-absorption is absorbed overhead minus actual overhead when positive; formula yields 5590 = $2000 over-absorption.
Why the others are wrong:
- A: Over-absorption amount is 1000.
- B: Direction is over-absorption, not under-absorption.
- C: Direction is over-absorption, not under-absorption.
Final answer: D
Topic: Traditional costing methods
Practice more A Level Accounting (9706) questions on mMCQ.me