A Level Accounting (9706)•9706/13/M/J/23
A Level Accounting (9706) — 9706/13/M/J/23, Question 27
A business marks up its products by 20% on cost to calculate a selling price. Each unit of product uses 4 hours of direct labour and 2 kilos of direct material. The correct overhead absorption rate to be used is $8 per labour hour. In error the book-keeper used a rate of $13 per labour hour. What was the effect on the selling price of one unit of product?

Answer choices
- A$5
- B$12
- C$20
- D$24
Explanation
Overhead Error Impact on Markup
Steps:
- Correct overhead per unit: 4 hours × 32.
- Erroneous overhead per unit: 4 hours × 52.
- Overstatement in unit cost: 32 = $20.
- Selling price markup is 20% on total cost, so overstatement in selling price: 24.
Why D is correct:
- Markup applies to full cost (including overhead), so cost error of 20 plus 20% markup on that error (24 per formula: SP = Cost × 1.20.
Why the others are wrong:
- A. $5: Ignores labor hours and markup entirely.
- B. $12: Applies 20% markup only to correct overhead, not the error.
- C. $20: Captures cost overstatement but omits markup on the error.
Final answer: D
Topic: Traditional costing methods