A Level Accounting (9706)•9706/12/M/J/23
A Level Accounting (9706) — 9706/12/M/J/23, Question 24
Which costs are charged to individual jobs in a job costing system?

Answer choices
- Adirect labour plus direct materials plus production overhead
- Bdirect labour plus direct materials
- Cdirect labour plus production overhead
- Ddirect materials plus production overhead
Explanation
Direct Costs in Job Costing Systems
Steps:
- Identify the purpose of job costing: to assign costs to specific jobs or orders for accurate pricing and profitability.
- Distinguish direct costs (traceable to individual jobs) from indirect costs (not traceable, like overhead).
- Recognize direct materials and direct labor as traceable to specific jobs.
- Exclude production overhead, which is allocated across all jobs, not charged directly.
Why B is correct:
- In job costing, only direct costs—direct labor and direct materials—are charged to individual jobs, as per standard cost accounting definitions, allowing precise tracking.
Why the others are wrong:
- A includes production overhead, which is indirect and allocated, not directly charged.
- C omits direct materials, a key traceable cost essential for job-specific tracking.
- D excludes direct labor, another directly traceable cost required for complete job costing.
Final answer: B
Topic: Traditional costing methods